Music City Makeover: New Equalization Facility Helps Nashville Wrestle with Water Overflows

The Clean Water Nashville program covers more than 70 projects, varying in size and scope. Earlier this year, workers completed the Gibson Creek Equalization Facility. The $18.9 million project includes a 10-million-gallon pre-stressed concrete tank and a 22-million-gallon-per-day pump station. Construction began in August 2021 and was completed in February 2024.

“The primary goal of the project is to improve the infrastructure due to a growing population and increase flow,’’ says Thomas Ward, assistant project manager at Reeves Young, the general contractor for the project.